Design basis for gypsum greenfield plant
The design basis starts with the rock, not the machine. Gypsum is rated at 20–60 MPa compressive strength with very low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.25 t/m³. Soft and prone to caking; drying and air-flow control in the grinding circuit matter more than crushing force. Measurements are only comparable when the sieve standard is the same.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 220 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of ground powder, 0–10 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gypsum · 20–60 MPa · abrasion very low |
| Design throughput | 220 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | ground powder, 0–10 mm |
| Loose bulk density | 1.25 t/m³ |
| Suggested circuit | impact / hammer → screen → grinding mill |

Why bag filter pressure drop appears in this circuit
Differential pressure across the dust collector rises and the mill loses air flow. In a gypsum greenfield plant this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.
- bags are blinded by fine or damp powder
- the cleaning pulse interval or pressure is wrong
- duct leakage reduces the effective extraction volume
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) trend differential pressure every shift; 2) measure air volume at the mill outlet and collector; 3) inspect pulse valves and compressed-air dryness. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For gypsum at 220 t/h the working train is impact / hammer → screen → grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gypsum and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~275 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.25 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 540 kW order-of-magnitude connected load |
The corrective actions for bag filter pressure drop are applied on top of this base circuit: set the pulse cycle from measured differential pressure; replace blinded bags and check hopper discharge; seal the ducting and verify air volume at the mill outlet.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 40% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Trend differential pressure every shift
- Measure air volume at the mill outlet and collector
- Inspect pulse valves and compressed-air dryness
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 220 t/h nominal |
| Grading | Full sieve analysis, agreed standard, ground powder, 0–10 mm |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 540 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gypsum, while a verifiable mass balance determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 220 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.