Design basis for dolomite contract crushing
The design basis starts with the rock, not the machine. Dolomite is rated at 60–180 MPa compressive strength with low–medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.42 t/m³. Suits impact crushing and downstream grinding; the fines fraction is often the most valuable product. A change in one stage changes the circulating load in all the others.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of aggregate, agricultural lime, filler powder.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Dolomite · 60–180 MPa · abrasion low–medium |
| Design throughput | 100 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | aggregate, agricultural lime, filler powder |
| Loose bulk density | 1.42 t/m³ |
| Suggested circuit | impact crusher → screen → optional Raymond mill |

Why powder moisture and caking appears in this circuit
Powder cakes in the silo and the finished product moisture drifts upward. In a dolomite contract crushing this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- feed surface moisture rises after rain or washing
- hot-air volume is insufficient for the evaporation load
- duct condensation forms at cold starts
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) measure feed and product moisture each shift; 2) log mill outlet temperature; 3) inspect ducting and the bag hopper for condensation. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For dolomite at 100 t/h the working train is impact crusher → screen → optional Raymond mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for dolomite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.42 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 220 kW order-of-magnitude connected load |
The corrective actions for powder moisture and caking are applied on top of this base circuit: add or uprate the drying stage and meter inlet moisture; balance hot-air volume with feed rate and outlet temperature; pre-heat the circuit and insulate cold duct sections.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 40% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Measure feed and product moisture each shift
- Log mill outlet temperature
- Inspect ducting and the bag hopper for condensation
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, aggregate, agricultural lime, filler powder |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 220 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for dolomite, while mobility and fast set-up determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.