Design basis for bauxite wet tropical climate
The design basis starts with the rock, not the machine. Bauxite is rated at 30–90 MPa compressive strength with low abrasiveness, high moisture sensitivity and a loose bulk density around 1.35 t/m³. Sticky, clay-rich feed blocks grizzlies and screens; wet processing and generous transfer chutes are usual. The reference conditions should be attached to every figure quoted.
A wet tropical climate must keep screening reliable through a long rainy season, constrained by high feed moisture and clay-bearing overburden. The commercial priority is wet screening and washing. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of sized ore and washed fines.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Bauxite · 30–90 MPa · abrasion low |
| Design throughput | 150 t/h saleable product (120–300 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | sized ore and washed fines |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | impact crusher → washing screen |

Why capacity shortfall appears in this circuit
The line stabilises at 70–85% of its quoted throughput. In a bauxite wet tropical climate this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- the mass balance was sized for fresh feed without circulating load
- a feeder or conveyor reaches its volumetric limit before the crusher does
- screen efficiency falls as near-size material builds up in the return loop
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) weigh the return belt over a full shift; 2) log crusher power draw against feeder rate; 3) sieve the screen oversize for near-size content. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For bauxite at 150 t/h the working train is impact crusher → washing screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for bauxite and for a softer rock. The reference conditions should be attached to every figure quoted.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~188 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | washing screen |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 440 kW order-of-magnitude connected load |
The corrective actions for capacity shortfall are applied on top of this base circuit: recalculate the full mass balance including the return stream; add surge capacity ahead of the secondary stage to hold choke feed; resize the limiting conveyor or screen deck rather than the crusher.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 50% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Weigh the return belt over a full shift
- Log crusher power draw against feeder rate
- Sieve the screen oversize for near-size content
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 150 t/h nominal |
| Grading | Full sieve analysis, agreed standard, sized ore and washed fines |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 440 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for bauxite, while wet screening and washing determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
The reference conditions should be attached to every figure quoted. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.