Configuration summary
400 TPH gold ore aggregate crushing and screening plant in Vietnam is an indicative HAMAC Machinery engineering reference configuration for Vietnam, not a record of a delivered plant. It sizes a 400 TPH line for gold ore from published equipment data; no customer name, contract value or commissioning date is claimed. Engineering reference for a 400-500 t/h gold ore aggregate crushing and screening plant in Vietnam, sized for primary and secondary crushing before milling. The configuration below is an indicative HAMAC circuit for this material and throughput; final equipment selection follows a material test, feed gradation, saleable product fractions and site power review. Figures are nominal and should be confirmed in a written proposal.
Engineering reference for a 400-500 t/h gold ore aggregate crushing and screening plant in Vietnam, sized for primary and secondary crushing before milling. The configuration below is an indicative HAMAC circuit for this material and throughput; final equipment selection follows a material test, feed gradation, saleable product fractions and site power review. Figures are nominal and should be confirmed in a written proposal.
| Parameter | Value |
|---|---|
| Raw Material | gold ore |
| Nominal Capacity | 400-500 t/h |
| Maximum Feeding Size | 1,000 mm |
| Output Size | 0-5, 5-20, 20-40, 40-80 mm |
| Primary Crusher | PE1500×1800 jaw crusher |
| Secondary Crusher | HPT800 cone crusher × 2 |
| Vibrating Screen | 4YK3075, 4 decks |
| Circuit | jaw + cone in closed circuit |
| Application | primary and secondary crushing before milling |
| Power & Layout | confirmed after site review |

Equipment configuration and process
The indicative configuration for this study is listed above. In HAMAC projects, the equipment list is fixed only after the raw material, feed gradation and saleable product fractions are confirmed — the same nominal capacity can require different crushers for basalt, limestone or river pebble.
A typical line of this size runs: vibrating feeder → primary jaw crusher → secondary cone or impact crusher → multi-deck vibrating screen → belt conveyors, with oversize returned in closed circuit. Dust suppression, washing and a magnetic separator are added where the feed or product specification requires them.
For a 400 TPH gold ore line in Vietnam, three inputs usually decide the final bill of materials: operator training and a recorded baseline of power draw, vibration and product gradation at hand-over make later troubleshooting measurable; dust-suppression water availability and the local discharge limit can add a bag filter or a washing stage that is not in a bare crusher list; a surge pile between the primary and secondary stages decouples the two crushers and protects throughput when the feed gradation swings. These are the points a HAMAC engineer checks against your own test data before the equipment list is fixed; the table above is therefore a starting specification rather than a quotation.
Compare similar plants in the project library or browse plant designs by capacity.
Delivery, installation and support
HAMAC's stated service scope covers initial consultation, solution design, site visit, production, shipment, installation supervision, commissioning, operator training, spare-parts supply and after-sales handling. For export projects the commercial scope is normally agreed as FOB, CFR or CIF, with local civil work and lifting equipment defined in the contract.
- Factory assembly and test before shipment
- Container / break-bulk loading plan with shipped spare parts and tools
- Installation drawings and commissioning supervision
- Operator training and recommended wear-parts stock list