400 TPH gold ore stationary crushing plant in Nigeria is an indicative HAMAC Machinery engineering reference configuration for Nigeria, not a record of a delivered plant. It sizes a 400 TPH line for gold ore from published equipment data; no customer name, contract value or commissioning date is claimed. Engineering reference for a 400-500 t/h gold ore stationary crushing plant in Nigeria, sized for primary and secondary crushing before milling. The configuration below is an indicative HAMAC circuit for this material and throughput; final equipment selection follows a material test, feed gradation, saleable product fractions and site power review. Figures are nominal and should be confirmed in a written proposal.
Engineering reference for a 400-500 t/h gold ore stationary crushing plant in Nigeria, sized for primary and secondary crushing before milling. The configuration below is an indicative HAMAC circuit for this material and throughput; final equipment selection follows a material test, feed gradation, saleable product fractions and site power review. Figures are nominal and should be confirmed in a written proposal.
| المعلمة | القيمة |
|---|---|
| المادة الخام | خام الذهب |
| الطاقة الاسمية | 400-500 طن/ساعة |
| أقصى حجم للتغذية | 1,000 mm |
| حجم الناتج | 0-5، 5-20، 20-40، 40-80 مم |
| الكسارة الأولية | PE1500×1800 كسارة الفك |
| الكسارة الثانوية | HPT800 كسارة مخروطية × 2 |
| الغربال الهزاز | 4YK3075، 4 مجموعات |
| الدائرة | الفك + المخروط في دائرة مغلقة |
| التطبيق | الطحن الأولي والثانوي قبل التكسير |
| الطاقة والتصميم | تم التأكيد بعد مراجعة الموقع |

تكوين المعدات والعملية
يرد أعلاه التكوين الإرشادي لهذه الدراسة. في مشاريع HAMAC، لا يتم تحديد قائمة المعدات إلا بعد التأكد من المواد الخام وتصنيف المواد الأولية وأجزاء المنتج القابلة للبيع — فقد تتطلب السعة الاسمية نفسها استخدام كسارات مختلفة للبازلت أو الحجر الجيري أو حصى الأنهار.
يتكون الخط النموذجي من هذا الحجم من: مغذي اهتزازي → كسارة فكّية أولية → كسارة مخروطية أو صدمية ثانوية → غربال اهتزازي متعدد الطبقات → ناقلات حزامية، مع إعادة المواد ذات الحجم الزائد إلى الدائرة المغلقة. ويتم إضافة أنظمة كبح الغبار والغسل والفاصل المغناطيسي عندما تتطلب مواصفات المواد الواردة أو المنتج ذلك.
For a 400 TPH gold ore line in Nigeria, three inputs usually decide the final bill of materials: the maximum feed dimension governs the feeder and the jaw inlet, while the required top product size governs the closed-side setting and the screen deck count; when the plant feeds a concrete or asphalt batching plant, stockpile segregation and the number of separate product bins become part of the layout; for manufactured sand, the fines content and particle shape spec can justify a VSI stage and a sand washer beyond a standard three-stage aggregate line. These are the points a HAMAC engineer checks against your own test data before the equipment list is fixed; the table above is therefore a starting specification rather than a quotation.
Compare similar plants in the project library or browse plant designs by capacity.
التسليم والتركيب والدعم
يشمل نطاق الخدمة المعلن عن HAMAC الاستشارة الأولية، وتصميم الحلول، وزيارة الموقع، والإنتاج، والشحن، والإشراف على التركيب، والتشغيل التجريبي، وتدريب المشغلين، وتوريد قطع الغيار، وخدمات ما بعد البيع. وبالنسبة لمشاريع التصدير، يتم الاتفاق عادةً على النطاق التجاري وفقًا لشروط FOB أو CFR أو CIF، مع تحديد الأعمال المدنية ومعدات الرفع المحلية في العقد.
- التجميع والاختبار في المصنع قبل الشحن
- خطة التحميل في حاويات / شحن جزئي مع قطع الغيار والأدوات المرسلة
- رسومات التركيب والإشراف على التشغيل التجريبي
- تدريب المشغلين وقائمة قطع التآكل الموصى بتخزينها